Street and Utility Rehabilitation and Wastewater Treatment Facility Improvements

May 2012 Newsletter

Schedule through the end of October
Larson Excavating will be placing topsoil, preparing the yards for seeding and reinstalling mailboxes over the next week.  They will also be placing gravel on any driveways that require it and preparing the project area for winter.

Please avoid driving over the new curb and gutter and driveway concrete until at least 7 days after it is placed.

Concrete Information
Concrete requires adequate time to cure and reach its design strength after it has been placed.  For this reason please do not drive over the curb and gutter or your driveway until at least 7 days after it has been placed. 

Your cooperation is appreciated to ensure a longer life for your new concrete curb and gutter and driveway.

Driveway Quotes

TCP Informational Flyer

Water and Sewer Contractors

List of local contractors that may install new sewer and water services from the shutoff at the right of way to your house.

Lester Waterworks – Directional Drilling
Les Wille
320.493.7169

Opatz Excavating
Ed Opatz
320.250.1363

Joe’s Countryside Excavating
Joe Paggen
320.253.6756

Lange Trenching
Dale or Jeff Lange
320.356.7976

Larson Excavating Contractors
Jeff Larson
320.746.2684