Rice Street/Highway 36 Interchange Construction

Notice

Rice Street final paving scheduled on Tuesday, September 27th and Wednesday, September 28th, 2011.


Table of Contents

Project Overview
Construction Schedule
Preferred Alternative Selected
Project Background
How have interchange alternatives been evaluated?
Public Project Documents


Project Overview

After 18 months of planning and design, the Highway 36 and Rice Street Interchange Project is under construction.  The project includes the replacement of the standard diamond interchange with an offset single-point interchange to improve intersection spacing as well as safety and capacity issues along Rice Street.  The Rice Street corridor is being converted from a three-lane section to a four-lane divided section with turn lanes, bike lanes, and sidewalks. 

Top


Construction Schedule

Completed Work

  • Tree removals in the Highway 36 right-of-way and along the Rice Street corridor
  • Private utility relocations including the burial of existing overhead utilities along Rice Street
  • Demolition of the existing Wonder Bakery, Sinclair gas station, Fortune House restaurant and the apartment building located on the southwest corner of Minnesota Avenue and Rice Street
  • Construction of the easterly portion of the new Rice Street bridge over Highway 36
  • Construction of County Road B2 West
  • Construction of County Road B West and Minnesota Avenue east of Rice Street
  • Watermain from Capitol View Avenue to Minnesota Avenue
  • Most of the Rice Street storm sewer
  • Some drainage improvements within the interchange area
  •  Noise wall construction

Scheduled Work

Winter 2010

  • Construction of the westerly portion of the new Rice Street bridge over Highway 36
  • Construction of ramp bridges over Highway 36

Spring/Summer 2011

  • Construction of the west half of new Rice Street
  • Construction of County Road B West and Minnesota Avenue west of Rice Street
  • Remaining storm sewer and stormwater ponding area and watermain construction

The Rice Street Bridge and the ramp bridges over Highway 36 are tentatively scheduled to be complete by early summer 2011.  Work on Rice Street and side streets is tentatively scheduled to be complete in summer 2011.  Minor work will continue into fall 2011.  The project completion date is October 28, 2011.

Top


Preferred Alternative Selected

January 2010 Open House Held - To provide an opportunity for all interested parties to review the Rice Street/Highway 36 Interchange and Rice Street preferred alternative layout, a public open house was held Wednesday, January 20, 2010 in the Rose Room at the City of Roseville Skating Center.

Based on detailed traffic analysis and public input, the Project Management Team has selected the Offset Single Point Interchange as the preferred alternative to be carried forward for further review in the environmental document The reason for this decision is identified below.

  • Provides the best long term traffic operations
  • Does the best job of accommodating bicycles and pedestrians
  • Allows for maintaining traffic during construction
  • Is most compatible with plans for a future park and ride in the SE quadrant of the interchange

The preferred alternative also includes improvements to the Rice Street corridor (Offset Single Point interchange) from CR B to CR B2 as indicated below:

  • The roadway would be reconstructed to 4-lanes and divided by a median
  • Turn lanes would be provided at select major intersections, as traffic volumes dictate

Stormwater and drainage improvements would be included to achieve watershed standards.

Top


Project Background

What is the Rice Street/Highway 36 Interchange Study?
Trunk Highway (TH) 36 is an important statewide corridor designated as a principal arterial, high-priority interregional corridor. Rice Street (CSAH 49) is a minor arterial that serves as an important reliever to I-35E. The growth of the general area has resulted in additional traffic and development pressures in the communities along TH 36 and the various north/south roadways serving the trunk highway. This project (S.P. 6212-165) addresses issues at the intersection of TH 36 and Rice Street. It includes the reconstruction of the Highway 36 and Rice Street interchange, and also improvements to Rice Street between County Road B-2 on the north end, and County Road B on the south. The project resides mostly in the city of Roseville, however portions of the project also enter the cities of Maplewood and Little Canada. Currently the project is in the Preliminary Engineering and Environmental Assessment phase, which will conclude in March 2010. There is no funding currently assigned for construction of the project; therefore a construction date has not yet been identified. Ramsey County is currently pursuing funding.

Why is the project necessary?
The purpose of the proposed Rice Street/Highway 36 interchange improvements is to address existing and future safety and operational deficiencies. The need for the project is driven by:

Anticipated increase in traffic volumes on Rice Street from 20,000 vehicles per day to (existing) to 27,200 vehicles per day (2033).

Additional concerns include:

  • Rice Street bridge over Highway 36 no longer meets current geometric standards
  • Rice Street bridge is in poor condition and eligible for federal bridge replacement funding.
  • Closely spaced intersections do not comply with current Mn/DOT access management standards and cause traffic flow issues
  • Pedestrian facilities are not continuous across TH 36 or Rice Street
  • As traffic volumes increase, safety and traffic operations will continue to deteriorate if existing deficiencies are not addressed.

Top


How have interchange alternatives been evaluated?

Mn/DOT initiated a brainstorming and internal screening effort to determine the range of feasible interchange concepts that would be reviewed by the Project Management Team. The Mn/DOT process resulted in five unique concepts. The consultant also developed additional concepts, and one of these were included in the initial screening process, for a total of six interchange concepts.

A level of service (LOS) analysis was conducted using year 2033 traffic forecasts to assess traffic capacity and operational characteristics for each of the six interchange concepts. Based on this analysis, three of the concepts were eliminated from further consideration. The remaining three concepts represent more traditional single point and diamond interchange types. These types appear to accommodate the forecast traffic volumes, operate at a high level of service, and present common design features that are understood by drivers. The remaining three interchange concepts included:

Within these three concepts, there are unique design options that were also considered and carried forward for further evaluation. Based on detailed operational analysis and a qualitative screening including such factors as construction cost, right-of-way impacts, and other social and environmental factors, an Offset Single Point interchange was selected as the Preferred Alternative.

Top


 

Partner Logos

Public Project Documents: 
application/pdf iconProject Location Map — 159.31 KB
application/pdf iconMay 2009 - Newsletter — 3.85 MB
application/pdf iconAugust 2010 Pictures — 2.08 MB
application/pdf iconSeptember 2010 Pictures — 544.41 KB
application/pdf iconOctober 2010 Pictures — 1.98 MB
application/pdf iconNovember 2010 Pictures — 1022.91 KB
application/pdf iconJanuary 2011 Pictures — 257.12 KB
application/pdf iconApril 2011 Pictures — 182.46 KB
application/pdf iconConstruction Updates — 77.08 KB