Construction Cost: $215,000
Features
-
Improved pedestrian and vehicular access to Junior High School
-
Provided separation of bus traffic and parental traffic for drop-off and pick-up times
-
Provided one way traffic flow for student drop-off and pick-up
-
Provided raised sidewalks for safe pedestrian access to school from parking lots and adjacent residential areas
-
Increased number of visitor and teacher parking stalls
SEH Services
-
Provided complete design, bidding, and construction services for project
-
Worked with Village, School District, and WisDOT to meet needs of each entity
-
Broke project into alternatives to best utilize the grant funding and stay within the school district budget
-
Provided design, bidding and construction documentation to WisDOT for Safe Routes to School grant funding