SEH provided the City of Burnsville traffic and municipal engineering services for the installation of a new traffic signal system at Southcross Drive and Burnhaven Drive. Project scope also included mill-and-overlay design on Southcross Drive (between Burnhaven Drive and Grand Avenue), miscellaneous road and utility design modifications.
Features
-
Conducted field survey
-
Prepared Signal Justification Report
-
Signal system design included advance EVP detection on three of the four intersection approaches, LED indications, and interconnect to the nearby signal system at Buck Hill Road
-
Prepared signing and pavement marking plans
-
Traffic signal timing and coordination services
-
Miscellaneous road and utility adjustment work, including mill-and- overlay of Southcross Drive
-
Loop detector replacement design at Buck Hill Road and Grand Avenue signal systems
SEH Services
-
Traffic engineering
-
Municipal engineering
-
Traffic operative analysis
-
Design services
-
Construction services