Water Treatment Plant Improvements Project
City of Port Washington
Road Closures & Transportation Impacts
- No foreseen road closures or traffic impacts in the near future.
January 1, 2026 to January 31, 2026
- Interior painting
- Interior piping work
- Interior demolition
- Interior electric work
- Interior process equipment installation
- Sanitary sewer repair
- Underground utility work
December 1, 2025 to December 31, 2025
- Interior lighting
- Interior finishing work
- Interior painting
- Interior process equipment installation
- Interior lighting
- Interior electric work
- Interior demolition
- Garage door installation
November 1, 2025 to November 30, 2025
- Interior painting
- Exterior painting
- Interior electric work
- Interior piping work
- HVAC work
- Concrete finishing
- Interior finishing work
- Interior process equipment installation
- Exterior lighting
October 1, 2025 to October 31, 2025
- Exterior masonry
- Exterior lighting
- Pavement base preparation and paving
- Exterior painting
- Interior piping work
- Interior finishing work
- Interior electric work
- Interior concrete finishing
September 1, 2025 to September 30, 2025
The following construction activities are anticipated to occur:
- Exterior facade repairs
- Exterior painting
- Concrete finishing
- Exterior masonry
- Buried utilities installation
- Selective interior demolition
- Interior finishing work
- Interior piping work
- Interior electrical work
August 1, 2025 to August 31, 2025
The following construction activities are anticipated to occur:
- Exterior facade repairs
- Exterior painting
- Concrete finishing
- Exterior masonry
- Selective interior demolition
- Interior finishing work
- Interior piping work
- Interior electrical work
July 1, 2025 to July 30, 2025
The following construction activities are anticipated to occur:
- Grading modifications
- Exterior facade repairs
- Exterior painting
- Concrete finishing
- Selective interior demolition
- Interior finishing work
- Interior piping work
- Interior electrical work
- Leak testing of clearwell
- Buried pipe investigation & installation
For previous updates, visit Project Background/History
Construction Updates
The City has awarded the WTP Improvements Project to CD Smith Construction. The construction activities began in July 2024 and are scheduled to continue into the middle of 2026.
Construction Progress Photo Gallery
As construction progresses, relevant photos of the construction progress may be added to this section of the project webpage.
View past progress photos