Water Treatment Plant Improvements Project
City of Port Washington
Construction Look Ahead
- Exterior seeding
- Process equipment startup
- Interior chemical feed system work
July 1, 2026 to July 13, 2026
- Interior painting
- Process equipment startup
- Chemical feed system work
June 1, 2026 to June 30, 2026
- Fencing and trailer removal
- Fencing installation on south side
- Interior demolition
- Interior electrical work
- Interior painting
- Chemical feed system work
- Process equipment startup
- Top soil and seeding
May 1, 2026 to May 31, 2026
- Exterior painting
- Doors and frames painting
- Concrete finishing
- Interior piping work
- Interior process equipment installation
- Clearwell disinfection and startup planning
- Interior electric work
- Exterior grading
- Interior painting
- Process equipment startup
- Chemical feed system work
- Exterior paving
April 1, 2026 to April 30, 2026
- Exterior painting
- Doors and frames painting
- Concrete finishing
- Interior piping work
- Interior process equipment installation
- Clearwell disinfection and startup planning
- Interior electric work
- Exterior grading
- Exterior paving
April 1, 2026 to April 15, 2026
- Exterior painting
- Doors and frames painting
- Concrete finishing
- Interior piping work
- Interior process equipment installation
- Clearwell disinfection and startup planning
- Interior electric work
March 1, 2026 to March 31, 2026
- Interior painting
- Interior doors, frames, and hardware installation
- Interior piping work
- Interconnect piping work
- Interior electric work
- Interior process equipment installation
- Clearwell work and disinfection
February 1, 2026 to February 28, 2026
- Interior painting
- Interior doors, frames, and hardware installation
- Interior drywall finishing
- Interior piping work
- Interior electric work and lighting installation
- Interior process equipment installation
January 1, 2026 to January 31, 2026
- Interior painting
- Interior piping work
- Interior demolition
- Interior electric work
- Interior process equipment installation
- Sanitary sewer repair
- Underground utility work
For previous updates, visit Project Background/History
Construction Updates
The City has awarded the WTP Improvements Project to CD Smith Construction. The construction activities began in July 2024 and are scheduled to continue into the middle of 2026.
Construction Progress Photo Gallery
As construction progresses, relevant photos of the construction progress may be added to this section of the project webpage.