Water Treatment Plant Improvements Project
City of Port Washington

Road Closures & Transportation Disruptions

This section will be updated when future road closures are scheduled.


Construction Notices

Updated Tuesday, December 10, 2024

Concrete pours are planned for the days listed below. Multiple concrete trucks will be driving too and from the WTP. Long duration traffic disruptions are not anticipated.

  • Wednesday, December 11, 2024
  • Friday, December 13, 2024

Construction Look Ahead

Throughout the project construction, the City intends to update the project webpage with monthly construction updates providing community members with general construction activities anticipated to occur in the next month.

December 1, 2024 to December 31, 2024

The following construction activities are anticipated to occur:

  • Concrete formwork, rebar tying, and concrete pours
  • Selective interior demolition

November 1, 2024 to November 30, 2024

The following construction activities are anticipated to occur:

  • Installation of the compacted aggregate geopiers on the south side of the WTP. (Completed)
  • Rebar will be delivered on Monday, November 18
  • Concrete formwork and rebar tying
  • The first concrete pour is scheduled for Monday, November 25
  • Selective interior demolition

October 1, 2024 to October 31, 2024

The following construction activities are anticipated to occur:

  • Plant 2 pumping improvements for resiliency and redundancy while Plant 1 is removed from service
  • Rough excavation and exploration on south side of WTP in preparation for new construction
  • Selective interior demolition
  • Buried utility piping modifications on the south side of the WTP
  • Shutdown of Plant 1
  • Installation of compacted aggregate geopiers on south side of WTP

September 1, 2024 to September 31, 2024

  • Rough excavation and exploration on south side of WTP in preparation for new construction
  • Electrical service modifications
  • Generator startup and testing
  • Preparation and planning for Plant 2 pumping improvements for resiliency and redundancy while Plant 1 is removed from service
  • Selective interior demolition

July 23, 2024 to August 31, 2024

The following construction activities are anticipated to occur between July 23, 2024 and August 31, 2024.  

  • Closure of the Lake Shore Path alongside of the WTP
  • Installation of construction security fencing
  • Installation of the new generator
  • Tree and top soil removal
  • Excavation on the south side of the WTP
  • Buried water main and sanitary sewer relocation
  • Installation of geo-piers to support the new structures on the south side of the WTP

Please note, this is a preliminary list and the items listed below are subject to change.  

Construction Updates

The City has awarded the WTP Improvements Project to CD Smith Construction.  The construction activities began in July 2024 and are scheduled to continue into the middle of 2026.

Construction Progress Photo Gallery

As construction progresses, relevant photos of the construction progress may be added to this section of the project webpage.

IMG_8314
DJI_20241126144643_0134_D
DJI_20241126091310_0117_D
DJI_20241126091526_0127_D
pw_001f
pw_002f
9-18-2024-Topsoil-Removal-1
9-18-2024-Topsoil-Removal-4
DJI_20240821094936_0039_D
DJI_20240821095114_0046_D
DJI_20240821095529_0055_D
DJI_20240730075358_0012_D
DJI_20240730082544_0018_D
DJI_20240731082310_0023_D
WTP-North-Sidewalk-7-26-2024
WTP-North-Path-7-26-2024
WTP-South-Path-7-26-2024
WTP-South-Sidewalk-7-26-2024
WTP-Fencing-Overview-7-26-2024